For this roofing access project, our experienced Crawley scaffolders installed a 6-lift high scaffold at Stone Court, Maidenbower, Crawley, West Sussex, to repair the verge tiles on the main gable and the dormer roofs on either side.
The main scaffold measured approximately 8 linear metres long by 10 metres high, with five lifts and working platforms four boards deep. The top lift extended to approximately 10 metres, with a cantilevered section over the car park entrance using 6-metre-long, 450mm-deep scaffold beams.
A further small working platform was required above the main scaffold to reach the peak of the gable. At approximately 12 metres high, we erected a 2.4-metre table lift, four boards deep, with Monarflex fitted around this upper section to help prevent debris falling into the car park below.
The scaffold was supplied for 12 weeks at £2,400 + VAT.
The roofing contractors needed to work on both the verge tiles running up the gable end and the dormer roofs on either side.
Five lifts brought the main scaffold to approximately 10 metres high, with the upper working platform running across the roofline. The platforms were constructed four boards deep to provide the working levels required for the repairs.
As the gable continued above the main scaffold, we installed a further working platform at approximately 12 metres high to provide access to the peak.
Part of the upper working platform required a cantilevered scaffold for awkward access above the car park entrance below.
To achieve this, we used 6-metre-long, 450mm-deep scaffold beams to support the cantilevered section of the top lift. The beams allowed the platform to extend across the entrance without placing scaffold standards directly beneath this section.
The main scaffold was approximately 8 metres long, while the cantilevered top lift created an upper working platform approximately 10 metres in length.
The two returns differed in depth, as shown in the photographs, with the left-hand return approximately two boards deep and the right-hand return approximately five boards deep.
We also erected a 2.4-metre-long table lift at approximately 12 metres high, specifically for access to the upper part of the gable. The platform was four boards deep and positioned directly in front of the peak where the highest verge tile repairs were required.
This upper platform rose above the main scaffold in both photographs and provided the additional working height the roofers needed to reach the top of the gable.
At approximately 12 metres high, the table lift was the highest working level on the scaffold. We fitted Monarflex sheeting around this upper working section to help prevent debris from falling into the car park below.
Rather than sheeting the entire scaffold, we installed Monarflex around the elevated section where work was taking place on the gable.
The sheeting enclosed the front of the working sections while leaving the remainder of the scaffold open.
The car park entrance also influenced how we secured the scaffold to the building.
Rakers were not suitable for this structure because they would have interfered with access into the car park. We therefore used Apollo ties to anchor the scaffold directly to the wall.
We installed the Apollo ties on the end pair of standards and every other pair, with ties positioned on the first, third, and fifth lifts.
This provided the required anchorage without rakers projecting out from the scaffold into the access area below.
On the 5th scaffold lift, we erected 2 small returns approximately one metre long to provide additional fall prevention around the ends of the working area.
The return platform on the left-hand side was approximately two boards deep, while the return on the right-hand end was approximately five boards deep.
No ladder access was installed for this scaffold project.
The roofing contractors could access the working platforms from the dormers on either side of the gable, removing the need to incorporate a separate ladder access into the scaffold.
12-Week Scaffold Hire at Stone Court, Crawley
The completed scaffold remained at Stone Court in Maidenbower, Crawley, for a 12-week hire period while the verge tile and dormer roof repairs were carried out.
Our scaffolders also installed an access scaffold for an AC installation at Fleming Way, Crawley, where contractors needed a working platform to reach the exterior of the Vent-Axia building.
That scaffold was a 2.4-metre tower approximately 6 metres high, with three lifts and a five-board-deep working platform. The project was completed urgently, and the scaffold remained in place for four weeks.
While considerably smaller than the scaffold at Stone Court, both projects required purpose-built access for contractors working at height in Crawley.